Interim works were completed by Sisk in 1999.

Phase 2 commenced in 2000 and delivered:

  • Replacement facilities linked to existing hospital
  • Refurbishments/upgrades in medical records, staff changing, concourse area, administration, wards and ultra-sound/CAT scan
  • New wards in Blocks 2 A & 2 C in 3 & 4-storey units
  • Block 2 B offices/entrance
  • Radiotherapy centre

Live 24 hour operational hospital environment

  • 2,000 hospital staff
  • 15,000 hospital visitors per day
  • 45 separate partial possessions were handed over in the course of the works
  • 1.5million man-hours
  • 533 separate subcontractors/suppliers managed, monitored & controlled for production, cost control, schedule adherence and Quality.