Sisk provided an additional 44 bed spaces, over 2,400m² of floor space above the existing facility. The majority of the new bed space is made up of single or semi-private rooms all of which contain their own ensuite bathrooms.

As a section of the project involved the conversion of the existing roof into clinical space as well as other interfaces within the live hospital environment, noise and dust monitoring were critical elements in the management process with monitoring stations set up in pre-agreed locations and results issued weekly