A19-A1058 Coast Road Junction - First Bridge Beams Installed

Our A19-A1058 Coast Road scheme being delivered for Highways England in Newcastle upon Type reached a significant milestone in June when the bridge beams to the first of the six new bridges being built on the scheme were installed.
 
The 19 beams ranging in weight from 25 tonnes to 57 tonnes were installed successfully over a 24 hour period using a 400 tonne crane initially and the 400 tonne and a 250 tonne crane working in tandem for the heavier precast edge beams.
 

17.06.17

Sisk Steconfer JV begin testing trams on new Luas Cross City extension

Sisk Steconfer JV has commenced testing the trams on the new Luas Cross City light rail extension in Dublin, the most significant milestone for the project to date.

Running from St Stephen’s Green to Broombridge through the city centre, Phibsborough and Cabra, the new line will link the Luas Red and Green Lines.

Source : Irish Building magazine
16.05.17

Considerate Constructors Scheme launches in Ireland

From left to right: Ken Lynch, Contracts Manager, The Exchange, Sisk; Paul Hackett, MD Ireland East, Sisk; Edward Hardy, Chief Executive of the Considerate Constructors Scheme; Brian Handcock, Head of Sustainability, Sisk.
 

John Sisk & Son is the first contractor to register site